About DOE Button Organization Button News Button Contact Us Button
US Department of Energy Seal and Header Photo
Science and Technology Button Energy Sources Button Energy Efficiency Button The Environment Button Prices and Trends Button National Security Button Safety and Health Button
Office of Environmental Management

Executive Summary

The purpose of this Rocky Flats Closure Legacy report is to capture the successes and failures of the Rocky Flats closure experience. The Legacy report fulfills the guidance for capturing lessons learned found in the following DOE documents:

Although a substantial amount of information is provided, this document is not a template for success, since there is not a single recipe for this. There is no formula that can be applied to every site, since each site is different geographically, in terms of cleanup scope and future mission, and with different cultural and political issues. However, this document presents the experience at Rocky Flats to provoke thought about the vision, mission, project progress, and cooperation of the parties at other Environmental Management sites. And before the Rocky Flats experience is dismissed as an anomaly, it is hoped that some of the lessons from Rocky Flats will be carried forward and adapted to the closure experience at other sites.

Conversations between people that have contributed to the Rocky Flats Closure Project invariably lead to speculation as to why the project was successful. What is said and heard will depend upon the role played by the individuals...the regulators were cooperative...the contractor was incentivized and motivated...the DOE delivered most of its government furnished services and equipment on time...the budget appropriations were consistent and reliable at $650 million per year...closure was managed as a finite project and using project management principles...stakeholders were involved in project planning...workers were involved in work planning. While each person brings a unique perspective, most will agree that no single factor was responsible for achieving accelerated closure, but that in some measure all of these factors and more were necessary for success. Some observers have stated that Rocky Flats was lucky. While there was certainly a measure of good fortune, Rocky Flats was poised and willing to take advantage of it whenever it did materialize.

Beyond any specific innovation, it was through unparalleled cooperation among the interested parties that a conservative and compliant cleanup and closure of Rocky Flats was enabled; ahead of schedule, under cost, and without a fatality or serious injury. For some individuals, engagement in the process of closing and transitioning Rocky Flats was derived from a dedication to the vision and mission. For others it was a more calculated commitment to what was achievable. But regardless of motivation, and with the exception of a few citizen activist groups, each party recognized that it was at the confluence of interests, rather than the satisfaction of any one particular interest, that the vision of accelerated closure would be realized.

It was also realized that while the plant was undergoing risk reduction, the participants in the cleanup would need to take some political and programmatic risks if this project was to be successful. When Congress committed to the closure fund and to a 2006 closure for Rocky Flats they did not have available to them a final integrated project baseline. When the Kaiser-Hill Company L.L.C. (K-H) signed the cleanup contract, Site characterization was not complete and DOE had not lined up the necessary assistance from Carlsbad, Savannah River, Oak Ridge, Richland, LANL, LLNL, and others important to the success of Rocky Flats materials disposition. The regulators had not yet agreed to align project milestones with the lifecycle baseline. The community had not yet agreed to cleanup levels. Long standing issues of distrust needed to be overcome, yet, each of these organizations understood the opportunity to remove the risk from metropolitan Denver, to turn a liability into an asset and to focus on a common vision, even when disagreeing on some of the details. And so, while debates about issues such as cleanup levels, dirty demolition, landfill capping, and 903 Pad remediation were acrimonious at times, they did not cause the cleanup mission to unravel. And when external barriers to closure were encountered, these same groups were largely united in their efforts to remove the barriers.

There are many lessons-learned from the Rocky Flats Closure Project included in this report. Although it is recognized that these lessons are not always directly applicable to every DOE clean-up effort, it is hoped that in some way they can be beneficial to every DOE site, and in fact, any controversial cleanup effort. We consider the following lessons, summarized here and addressed in more detail later in the report, as universally applicable:

  • SAFETY IS JOB 1: This lesson was reinforced throughout the closure project. If work cannot be safely performed, then the project grinds to a halt. Early on in the project it was recognized that a significant investment in hazard identification, safety planning, and safety implementation during the actual work (i.e., the DOE’s Integrated Safety Management System) ensured that work was performed safely without unacceptable risks or unnecessary delays to correct safety deficiencies. Later in the project we came to understand that safety focus did not merely enable work, but facilitated efficiency and acceleration by building trust and engaging the workforce.
  • CONTRACT REFORM WORKS: The Rocky Flats “experiment” proved that the DOE’s contract reforms worked. The first K-H “Integrating Management” contract demonstrated that incentivizing clearly defined performance measures vastly improved actual results. In fact, the performance measures sometimes worked too well, incentivizing results at odds with the ultimate goals of the contract. The Closure Contract took the concept to the next level, providing large incentives to the company and the workers to safely and compliantly complete the clean-up and closure scope within a target scope and cost. Additional incentives for schedule and cost savings resulted in closure more than one year ahead of schedule and $530 million under the contract budget.
  • “WHAT, NOT HOW”: The DOE must manage to a contract, not manage the work for the contractor. The contractor must learn to respond to contractual direction and not DOE informal requests. This was a difficult transition at Rocky Flats due to years of conditioning from the “Management & Operations” contract approach typical at large DOE sites. Ultimately, the DOE Rocky Flats learned (although not perfectly) to define the work scope and standards that must be met and observe, evaluate, and report to the manager and contracting officer regarding the contractor’s performance on the terms of the contract. This did not undermine, but enhanced DOE’s safety and compliance oversight because the contract clearly required the contractor to work safely and compliantly in accordance with clearly defined requirements in the contract. Ultimately DOE’s safety and compliance oversight became more objective and technical issues became less subjective as the DOE was forced to clearly cite a contractual non-compliance that required correction per the contract.
  • COLLABORATIVE WORKING RELATIONSHIPS: As described in detail throughout this report, the Rocky Flats Closure was successful because the stakeholders (in the broadest sense of the word) were engaged in the process and supportive of the ultimate goal. The interests of numerous key figures, including Members of Congress, senior DOE management, state and local elected officials, and state and federal regulators, were actively solicited and ultimately met – the regulatory cleanup agreement, closure contract, desired end state and project parameters were brought to convergence. We communicated openly and often to seek the best solutions, and came to value the input from formerly dogmatic opponents. Although there were differences in the details, the entire Rocky Flats community shared a common goal: Make It Safe - Clean It Up - Close It Down.
  • DON’T WAIT FOR ALL GREEN LIGHTS, BE READY: As the analogy states, “If we waited for every light to be green we would never get anywhere.” The Site moved steadily, ploddingly, painfully, but inexorably toward one goal: 2006 Closure. Early in the project this goal seemed unachievable, in 2003 we started to believe we could beat 2006, and by 2004 the momentum was established to finish in 2005. Nonetheless, if we had focused on what we couldn’t do in 1995, when K-H took over the Site, or 1999, when the DOE was trying to open WIPP, or 2002, when we were fighting in court to ship plutonium to SRS, or throughout the project as we debated “how clean is clean enough?” then we would still be sitting here talking about when will Rocky Flats be done. The fact is, we’re done! We didn’t have all the answers at the beginning but we made course corrections along the way. Good fortune favors those ready to take advantage of the opportunity and momentum builds with progress. Define your goal and get moving!

We hope you can use this report and its lessons as a springboard for action at your respective sites. It is the sincere hope of everyone involved with the Rocky Flats Closure Project that the legacy of Rocky Flats will not be “Look what we did here” but rather, “Look what started here.”

 

The White House FirstGov.gov E-gov IQ FOIA
U.S. Department of Energy | 1000 Independence Ave., SW | Washington, DC 20585
1-800-dial-DOE | f/202-586-4403 | e/General Contact

Web Policies Button No Fear Act Button Site Map Button Privacy Button Phone Book Button Employment Button