|
The purpose of this Rocky Flats Closure Legacy report is to capture the successes
and failures of the Rocky Flats closure experience. The Legacy report fulfills the
guidance for capturing lessons learned found in the following DOE documents:
Although a substantial amount of information is provided, this document is not
a template for success, since there is not a single recipe for this. There is
no formula that can be applied to every site, since each site is different
geographically, in terms of cleanup scope and future mission, and with different
cultural and political issues. However, this document presents the experience
at Rocky Flats to provoke thought about the vision, mission, project progress,
and cooperation of the parties at other Environmental Management sites. And before
the Rocky Flats experience is dismissed as an anomaly, it is hoped that some of
the lessons from Rocky Flats will be carried forward and adapted to the closure
experience at other sites.
Conversations between people that have contributed to the Rocky Flats Closure
Project invariably lead to speculation as to why the project was successful.
What is said and heard will depend upon the
role played by the individuals...the regulators were cooperative...the contractor
was incentivized and motivated...the DOE delivered most of its government
furnished services and equipment on time...the budget appropriations were
consistent and reliable at $650 million per year...closure was managed as a
finite project and using project management principles...stakeholders were
involved in project planning...workers were involved in work planning.
While each person brings a unique
perspective, most will agree that no single factor was responsible for
achieving accelerated closure, but that in some measure all of these factors
and more were necessary for success. Some observers have stated that Rocky Flats
was lucky. While there was certainly a measure of good
fortune, Rocky Flats was poised and willing to take advantage of it whenever it
did materialize.
Beyond any specific innovation,
it was through unparalleled cooperation among the interested parties that a
conservative and compliant cleanup and closure of Rocky Flats was enabled;
ahead of schedule, under cost, and without a fatality or serious injury. For
some individuals, engagement in the process
of closing and transitioning Rocky Flats was derived from a dedication to the
vision and mission. For others it was a
more calculated commitment to what was achievable. But regardless of motivation, and with the
exception of a few citizen activist groups, each party recognized that it was
at the confluence of interests, rather than the satisfaction of any one
particular interest, that the vision of accelerated closure would be realized.
It was also realized that while
the plant was undergoing risk reduction, the participants in the cleanup would
need to take some political and programmatic risks if this project was to be
successful. When Congress committed to
the closure fund and to a 2006 closure for Rocky Flats they did not have
available to them a final integrated project baseline. When the Kaiser-Hill
Company L.L.C. (K-H)
signed the cleanup contract, Site characterization was not complete and DOE had
not lined up the necessary assistance from Carlsbad, Savannah River, Oak Ridge,
Richland, LANL, LLNL, and others important to the success of Rocky Flats materials disposition.
The regulators had not yet agreed to align project milestones with the lifecycle baseline.
The community had not yet agreed to cleanup levels. Long standing issues of distrust needed to be
overcome, yet, each of these organizations understood the opportunity to remove
the risk from metropolitan Denver, to turn a liability into an asset and to focus
on a common vision, even when disagreeing on some of the details. And
so, while debates about issues such as cleanup levels, dirty demolition,
landfill capping, and 903 Pad remediation were acrimonious at times, they did
not cause the cleanup mission to unravel. And when external barriers to closure
were encountered, these same
groups were largely united in their efforts to remove the barriers.
There are many lessons-learned
from the Rocky Flats Closure Project included in this report. Although it is
recognized that these lessons are not always directly applicable to every DOE
clean-up effort, it is hoped that in some way they can be beneficial to every
DOE site, and in fact, any controversial cleanup effort. We
consider the following lessons, summarized here and addressed in more detail
later in the report, as universally applicable:
- SAFETY IS JOB 1: This lesson was
reinforced throughout the closure project. If work cannot be safely
performed, then the project grinds to a
halt. Early on in the project it
was recognized that a significant investment in hazard identification,
safety planning, and safety implementation during the actual work (i.e.,
the DOE’s Integrated Safety Management System) ensured that work was
performed safely without unacceptable risks or unnecessary delays to
correct safety deficiencies. Later
in the project we came to understand that safety focus did not merely
enable work, but facilitated efficiency and acceleration by building trust
and engaging the workforce.
- CONTRACT REFORM WORKS: The Rocky
Flats “experiment” proved that the DOE’s contract reforms worked.
The first K-H “Integrating Management”
contract demonstrated that incentivizing clearly defined performance
measures vastly improved actual results. In fact, the performance measures
sometimes worked too well,
incentivizing results at odds with the ultimate goals of the contract.
The Closure Contract took the concept to
the next level, providing large incentives to the company and the workers
to safely and compliantly complete the clean-up and closure scope within a
target scope and cost. Additional
incentives for schedule and cost savings resulted in closure more than one
year ahead of schedule and $530 million under the contract budget.
- “WHAT, NOT HOW”: The DOE must
manage to a contract, not manage the work for the contractor. The contractor
must learn to respond to
contractual direction and not DOE informal requests. This was a difficult
transition at Rocky
Flats due to years of conditioning from the “Management & Operations”
contract approach typical at large DOE sites. Ultimately, the DOE Rocky Flats
learned (although not perfectly) to define the work scope and standards that must
be met and observe, evaluate, and report to the manager and contracting
officer regarding the contractor’s performance on the terms of the
contract. This did not undermine,
but enhanced DOE’s safety and compliance oversight because the contract
clearly required the contractor to work safely and compliantly in
accordance with clearly defined requirements in the contract. Ultimately
DOE’s safety and compliance
oversight became more objective and technical issues became less
subjective as the DOE was forced to clearly cite a contractual
non-compliance that required correction per the contract.
- COLLABORATIVE WORKING RELATIONSHIPS: As
described in detail throughout this report, the Rocky Flats Closure was
successful because the stakeholders (in the broadest sense of the word)
were engaged in the process and supportive of the ultimate goal. The
interests of numerous key figures,
including Members of Congress, senior DOE management, state and local
elected officials, and state and federal regulators, were actively
solicited and ultimately met – the regulatory cleanup agreement, closure
contract, desired end state and project parameters were brought to
convergence. We communicated openly
and often to seek the best solutions, and came to value the input from
formerly dogmatic opponents. Although there were differences in the
details, the entire Rocky Flats community shared a common goal:
Make It Safe - Clean It Up - Close It Down.
- DON’T WAIT FOR ALL GREEN LIGHTS, BE READY: As the analogy
states, “If we waited for every light to be green we would never get anywhere.”
The Site moved steadily, ploddingly, painfully, but inexorably
toward one goal: 2006 Closure. Early in the project this goal seemed
unachievable, in 2003 we
started to believe we could beat 2006, and by 2004 the momentum was
established to finish in 2005. Nonetheless, if we had focused on what
we couldn’t do in 1995, when
K-H took over the Site, or 1999, when the DOE was trying to open WIPP, or
2002, when we were fighting in court to ship plutonium to SRS, or
throughout the project as we debated “how clean is clean enough?” then we
would still be sitting here talking about when will Rocky Flats be done.
The fact is, we’re done! We didn’t have all the answers at the
beginning but we made course corrections along the way. Good fortune
favors those ready to take
advantage of the opportunity and momentum builds with progress.
Define your goal and get moving!
We hope you can use this report and its lessons as a
springboard for action at your respective sites. It is the sincere hope of everyone involved
with the Rocky Flats Closure Project that the legacy of Rocky Flats will not be
“Look what we did here” but rather, “Look what started here.”
|
 |